Why construction workers keep braving 150m high job

CONSTRUCTION workers braving heights of 150 metres have returned to their unique offices this year to paint and repair one of Gladstone Power Station's stacks.

Grey Construction Propriety Limited returned to the Gladstone Power Station after a Christmas break to begin an internal check on stack two at the power station.

The $1 million work, as part of an upgrade that happens once every 15 years, is to ensure the stacks are safe to operate through to 2030.

The same work will be completed on stacks one and three in 2019 and 2021 respectively.

 

Grey Constructions will continue their work this year at the Gladstone Power Station stacks.
Grey Constructions will continue their work this year at the Gladstone Power Station stacks.

Meanwhile NRG is looking to hire 80 - 100 people for shutdowns of units one and four this year.

The overhauls will involve inspections and repairs of the boiler and steam turbine, and a boiler tube clean.

Each will take 56 days, with unit one starting on February 23 and unit four on May 11.



Gallery: Yeppoon Races - check out the fashions on the field

Gallery: Yeppoon Races - check out the fashions on the field

Were you snapped by our photographer at the races?

Doblo says Rookwood won't have enough water for agriculture

Doblo says Rookwood won't have enough water for agriculture

He reopens the debate on "thinking big” about the Gap Dam project.

Battle of the beach as Yeppoon, Emu Park face off tonight

Battle of the beach as Yeppoon, Emu Park face off tonight

Seagulls looking to extend their unbeaten run in local league

Local Partners